Shoring
Day 11

Day 11

The temporary power pole was delivered and installed today, but it will not be inspected until Monday since the city is closed every Friday. I drove down to Torrance to pay Edison for connection and disconnection fees for the temporary pole and called the Edison customer service line to establish my service account. After the...
Day 10

Day 10

The 312B excavator was dropped back off at our lot this morning. I hope it had fun on its field trip, now it needs to get back to work. A matching string was pulled along the west side of the property (left of the video) to give a constant reference point to the west property...
Day 9

Day 9

The Caterpillar 312B Hydraulic Excavator was taken to another job site early this morning, but don’t worry – it will be back tomorrow. As for site work today, all of the shoring piles on the east side of the property (right side of the video) were marked in the soil. Unfortunately part of the neighbor’s...
Day 8

Day 8

Another slow day, however there was at least some progress. The sewer line was located and capped just inside the property line today, officially marking the end of demolition. A line was pulled along the east side of the property to mark the height of the first floor and to provide a constant reference to...