Retaining Walls
Day 14

Day 14

The shoring drill rig will be dropped off at 9am tomorrow, followed by the first half of the I-beams between 11am and noon. Even though drilling will not start until Monday (May 9th), today was spent making final preparations for the shoring piles. This included cutting small 2ft wide strips out of the 100 year...
Day 7

Day 7

After meeting with the demo/shoring/excavation/concrete contractor in the morning (Jason), he agreed that the existing 100 year old retaining walls need to be replaced. Jason’s second in command, Jeff, came back to survey the situation. Details of the existing conditions have been sent to the civil engineer so that he can determine what will be...