Today was pretty slow on our construction site, since most of my contractor’s crew was focused on the sidewalk and driveway next door. These needed to be re-poured because they were removed yesterday to allow them to finish the underground utility conduits. The only real on-site work was to increase the depth of the excavation next to the east wall (right of video), which required a few more pieces of lagging to be installed.

Dirt export truck-load total: 126 loads.