An amazing amount of progress was made today! The lagging crew managed to finish almost all of the west wall (left side of video) leading up to the utility pole. In addition, 15 loads of dirt were taken off the site.

Good progress is also being made on moving the neighbors’ utilities underground. The street crossing was completed today, as was the trench down their driveway. Tomorrow everything will be filled back in and the sidewalk will be poured. The pole should be gone in about two weeks!

Dirt export truck-load total: 126 loads.