190 pieces of treated 12″x4″x12′ lumber were delivered this morning (don’t blink, or you will miss it in the video). Excavation can finally continue, but first the lagging needs to be put in place. The crew started with most difficult section of lagging, which is where the positioning transitions from inside the flanges to behind the flanges. This transition allows the garage to extend in to the setbacks, since the finished basement (living space) is not allowed to.

One of these days I will post some photos from ground level of the lagging…